Portugal
Mota-Engil Consortium will build first phase of Luanda metro
Publication: ECO
Author: André Veríssimo
Source published: 26/09/2026, 16:53:53 UTC
Briefing created: 26/09/2026, 17:14:19 UTC
Based on a feed excerpt; full article content has not been acquired. Source evidence retrieved 26/09/2026, 17:11:24 UTC.
Briefings
Portuguese construction firm Mota-Engil is executing the first phase of Luanda's metro surface project, a 60 km segment funded by a 2.25 billion USD contract alongside Angolan partners. The project, part of a broader 149 km system, began formalizing in September 2024 with a total investment of 2.5 billion USD, with Portugal guaranteeing 233.5 million USD for the first phase. Construction was initially projected for 2025, though delays have occurred. The evidence covers the consortium structure, financial figures, and timeline up to September 2026, but does not confirm final completion dates or operational status.
Key points
- Mota-Engil, the 55th largest construction company globally, is executing the first phase of Luanda's metro surface project alongside Omatapalo and Griner Engenharia.
- The first phase spans approximately 60 kilometers along the Avenida Fidel Castro route and the ZEE to Airport Dr. António Agostinho Neto line.
Context and limitations
Evidence covers the consortium structure, financial figures, and timeline up to September 2026. Final completion dates and operational status remain uncertain due to reported delays and ongoing project management.
Generated by Bittrees-hosted qwen35-2b sha256:aaf42c8b7c3c on 26/09/2026, 17:14:19 UTC. Based on publisher-provided feed evidence; may not cover the full original article. Check the source for details.
View archived briefing on IPFS
bafybeiewsgji6bvfjp5k7rsoju6uvgfxv52eqqez7touogntfw35qk4o44